Parramatta - Source Control
Completion of 7 sites of the Parramatta Source Control Package. The sites consisted of:
Lavinia St - Excavate, lay, and backfill approx 30m of DN300 pipe. Construct 1 x DN1200 MH and 1 x valve chamber.
Monterey St - Excavate, lay, and backfill approx 100m of DN300 pipe. Construct 1 x Weir chamber and 1 x valve chamber.
Jubilee Park - Excavate, lay, and backfill approx 30m of DN600 pipe. Construct 1 x Weir chamber and 1 x valve chamber.
Goodhall Ave - Excavate 5m deep, lay, and backfill approx 16m of DN300 pipe. Construct 1 x Weir chamber and 1 x valve chamber.
Langdon Rd - Excavate, lay, and backfill approx 26m of DN300 pipe. Construct 1 x DN1200 MH and 1 x combined weir and valve chamber.
Sherwood St - Excavate, lay, and backfill approx 7m of DN300 pipe. Construct a valve chamber and install a sandstone rock on the bank for stabilisation.
Moxham Rd - Excavate, lay, and backfill approx 10m of DN600 pipe. Construct a valve chamber on the side of a riverbank. Install permanent access for SWC via council satisfied solution of sandstone steps.